This project, located on the Kent State University campus, will paint the 250,000-ground tank, abandon the 400,000-gallon ground tank, and provide overflow modifications and safety upgrades to the 250,000 ground and the 250,000 elevated tanks.
The project cost is $433,000. Bids were opened in mid-March 2022 and work is expected to begin in June.