Project Location:
State Route 59 from Longmere Dr to Willow St
Project Budget: $650,000 (2008-2010)
Project Schedule:
Design Start
Date May 2008
Construction
Start Date October 2008
Project Finish August 2010
Haymaker Parkway
In 2007, the street light foundations along Haymaker Parkway (SR 59) from
Longmere Drive to Willow Street were identified as having corroded anchor bolts.
An inventory was then completed to determine the extent of pole foundations
affected. It was determined that the majority of pole bases on the north side of
Haymaker Parkway were in need of repair.
The anchor bolts are embedded into
the concrete foundation and bolted to the light pole.
(Section A-A)
Currently, an investigation is being completed to determine the best method
to repair or possibly replace the light pole foundations.
The project provides for the design and phased repair/replacement of the
street light pole foundations along this section of roadway in 2008, 2009 and
2010.
Project Status:
- Consultant studying repair methods
|
Contact:
Jon Giaquinto, P.E
Senior Engineer
Phone:
330-678-8106
Email:
giaquintoj@kent-ohio.org |
 |
City of Kent
Department of Public Service
Division of Engineering |
|
|