Project Location:
Riverside Court
Project Budget: $75,000
Project Schedule:
Planning
Start Date November 2007
Construction
Start Date December 2008
Project Finish April 2009
Riverside Court
The existing waterline on Riverside Court is a 1 ¼" pipe that was installed
in the year 1924.
The Riverside Court Watermain project involves the construction a 6 inch
waterline to serve 8 properties and provide a new fire hydrant.
Upon investigating the existing roadway conditions, it was determined that
the needs for this area were greater than anticipated.
The pavement, curb, and sidewalk along with the sanitary sewer are in need of
upgrade and/or improvement.
This project is still in the planning stages.
A public meeting will be held to receive input and discuss the alternatives
prior to designing the future improvements.
Project Status:
The Riverside Court Watermain project is currently in the planning phase.
|
Contact: Rhonda Boyd, P.E., P.S.
Senior Engineer
Phone: 330-678-8106
Email:
boyd@kent-ohio.org |
 |
City of Kent
Department of Public Service
Division of Engineering |
|
|
|
|
|