Project Location: Riverside Court

 

Project Budget: $75,000

Project Schedule:

     Planning Start Date          November 2007

     Construction Start Date   December 2008

     Project Finish                    April 2009

 

Riverside Court

The existing waterline on Riverside Court is a 1 ¼" pipe that was installed in the year 1924.

The Riverside Court Watermain project involves the construction a 6 inch waterline to serve 8 properties and provide a new fire hydrant.

Upon investigating the existing roadway conditions, it was determined that the needs for this area were greater than anticipated.

The pavement, curb, and sidewalk along with the sanitary sewer are in need of upgrade and/or improvement.

 

 

This project is still in the planning stages.

A public meeting will be held to receive input and discuss the alternatives prior to designing the future improvements.

 

 

 


Project Status:

The Riverside Court Watermain project is currently in the planning phase.

  • Scope of project is currently being evaluated

  • Additional funding may be necessary

 

Contact: 

Rhonda Boyd, P.E., P.S.

Senior Engineer

Phone: 330-678-8106

Email: boyd@kent-ohio.org

  City of Kent

Department of Public Service

Division of Engineering