| |
|
Plum Creek
Stream Restoration
Project Location:
Mogadore Road at Plum Creek
Project Budget:
$1,550,000 ($1,063,359 funded by AARA
stimulus)
Project Schedule:
Design Start Date
June 2009
Construction Start Date February 2010
Project Finish
May 2011
Plum
Creek Stream Restoration Brochure
Plum Creek Stream Restoration
In March 2009,
the City of Kent applied for American Recovery and Reinvestment Act (ARRA)
stimulus funds for the Plum Creek Stream Restoration Project. The City of Kent
was awarded $1,366,527 for the planning, design, construction, and construction
management for the project. The Project includes the removal of the Plum Creek
Dam, replacement of the Mogadore Road Culvert, and the restoration of
approximately 2,200 linear feet of stream (upstream of the dam).

The Plum Creek Dam
was built in 1887 and no longer serves its original purpose. The dam is a Class
III structure under the jurisdiction of Ohio’s Dam Safety Laws regulated by the
Ohio Department of Natural Resources (ODNR) through periodic inspections. The
last inspection of the dam performed in 1995 resulted in recommendations for the
City to: prepare an Emergency Action Plan, prepare an Operation and Maintenance
Manual, perform hydrologic and hydraulic studies to determine modifications
needed to increase the discharge/storage capacity of the dam to pass the design
flood, prepare plans and specifications for the necessary modifications, and
rehabilitate the lake drain and install an adequate silting basin. No action
has been taken on these recommendations to date.
The existing
Mogadore Road Culvert is over 20 years old and is in poor condition. The 2008
Bridge Inspection Report noted the following existing issues: several bolts
rusted, the culvert is bulging in two locations, water is running under the
entire culvert length, the ground is washed out at the outlet 4.5 feet deep,
both headwalls need replaced. Many of the existing conditions mentioned above
go back at least as far as the 1985 Bridge Inspection Report. The conditions
have deteriorated over the years.
The Plum Creek
Reservoir, adjacent to Plum Creek Park, was last dredged in 1978. Approximately
24,000 cubic yards of material was removed from the reservoir in dredging and
rechanneling operations and a 40-foot x 9-foot silt basin was constructed. The
reservoir was reportedly in need of being dredged again by the early 1990’s. In
2009, the estimated amount of sediment in the reservoir is 12,000 cubic yards.
The soft sediment poses safety and aesthetic concerns. The impoundment also
negatively alters water temperature, dissolved oxygen, and turbidity (relative
clarity). The resultant water quality and physical barrier of the dam
negatively impact the diversity, quantity and quality of fish and
macroinvertebrates in the stream.
Project Status: -Construction
begins in February 2010.
|
Contact
Cori Finney, P.E.
Senior Engineer
Phone: 330-678-8106
Email:
finneyc@kent-ohio.org |
 |
City of Kent
Department
of Public Service
Division of
Engineering
|
|
|