Middlebury Road Watermain

 

Project Location:                  Middlebury Road

Project Budget:                     $550,000

Project Schedule:

     Design Start Date              June 2008

     Construction Start Date    April 2009

     Project Finish                     November 2009

 

Middlebury Road

The City of Kent Service Department has recorded 17 total waterline breaks along the existing Middlebury Road watermain since the year 2000. Recently, there has been an increase in frequency of breaks.

The existing Middlebury Road waterline is an 8-inch cast iron pipe constructed in the year 1960.

Approximately 3,500 feet of watermain replacement is proposed.

This project will tie into the new Middlebury/Cherry watermain and continue northeast along Middlebury Road, terminating with a connection into the Longmere Drive watermain.

Pending design and available funding, this project could be expanded to encompass the north side of the Wheeling & Lake Erie Railroad tracks.

 

 


Project Status:

The Middlebury Road Water Main project design phase is scheduled to begin June 2008..

  • Base mapping and record documents are being compiled

 

Contact: 

Cori Finney, P.E.   

Senior Engineer

Phone: 330-678-8106

Email:  finneyc@kent-ohio.org

  City of Kent

Department of Public Service

Division of Engineering