Middlebury Road Watermain

      Project Location: Middlebury Road

      Project Budget: $550,000

      Project Schedule:

           Design Start Date           April 2009

           Construction Start Date Fall 2012

           Project Finish                  2013

 

The City of Kent Service Department has recorded 17 total waterline breaks along the existing Middlebury Road watermain since the year 2000.  Recently, there has been an increase in frequency of breaks. The City’s Central Maintenance Department has been responding to the breaks.  Approximately 3,500 feet of water main replacement is proposed.  This project will tie into the new Middlebury/Cherry water main and continue northeast along Middlebury Road, terminating with a connection into the Longmere Drive watermain.  The new 8 inch ductile iron pipe will be wrapped in plastic to protect it from corrosive soils.

The existing Middlebury Road waterline is an 8-inch cast iron pipe constructed in the year 1960.

WATERMAIN BREAK LOCATION\

 

Project Status:

  • Preliminary design plans and specifications have been submitted to the City for review

  • OPWC funding has been awarded

  • Project will be advertised spring 2012.

  • Construction will begin fall 2012

Contact: 

Cori Finney, P.E.   

Senior Engineer

Phone: 330-678-8106

Email:  finneyc@kent-ohio.org

  City of Kent

Department of Public Service