Harris/West Street Storm Water Improvement

Project Location:           Harris Street and West Street

Project Budget:              $130,000

Project Schedule:

      Design Start Date              January 2008

      Construction Start Date    May 2008

      Project Finish                     October 2008

 

Harris and West Street

The neighborhood of Cedar Street, Dodge Street, West Street and Harris Street has had a history of storm sewer problems over the years. The residents have reported storm water flooding problems during heavy rain events.

Prior flooding occurrences have been in part due to the blockage of a sandstone box culvert that outlets storm water flow under the ABC Railroad to Mogadore Road and the Cuyahoga River.

The proposed improvements will include the construction of a head wall with a trash rack, and stabilization of the stream channel banks.

 

Properties located on the south end of Dodge and Elm Streets, Cedar Street, Alley 24, West and Harris Street will also realize a benefit from the proposed improvements to the drainage outlet structure west of Harris that receives storm runoff from the aforementioned areas.

Funding for this project is from a Community Development Block Grant through the U.S. Department of Housing and Urban Development (HUD).

Additional Improvements will be constructed in the neighborhood if future grant funding becomes available. These improvements involve construction of storm sewer with catch basins and swales to collect drainage on West Street from Alley 24 north through the Harris Street intersection to the stone culvert crossing the Railroad.


Project Status:
  • Engineering has completed construction specifications and bid documents

  • Obtained the majority of work agreements from the Railroad and adjoining property owners

  • The Harris/West Storm project bid opened May 2, 2008

  • The apparent low bidder is C.U.E. LLC Excavating at $86,113

  • It is anticipated that construction will commence in July

 