Central Maintenance
Engineering
Vehicle Maintenance
Water Reclamation
Water Treatment

Harold/Stinaff St. Storm Sewer Project

                                                                            

Project Location: Harold Street and Stinaff Street

 

Project Budget: $950,000

 

Project Schedule:

          Planning Start Date              October 2007

          Construction Start Date       TBA 2009

          Project Finish                        TBA 2009

 

 

Harold and Stinaff Street

The Harold/Stinaff neighborhood has been experiencing standing water in the roadside ditches on Harold Street and along the east end of Stinaff Street.

The excess water is due in part to very little fall in the roadside ditches along Harold and the eastern portion of Stinaff Street.

The Harold/Stinaff Storm Sewer project will correct deficiencies by constructing storm sewers along Harold and Stinaff Street then along Major’s Lane to outlet into the Fairchild Avenue storm sewer system.

This improvement will provide additional motorist safety benefits as well by reducing premature pavement failure experienced by the standing water along the pavement edge.

 

                 

This project is being funded in part through the City of Kent Storm Water Utility Fund, Issue II Grant, and property owner assessments.

 

 

Project Status:


The Harold/Stinaff Storm Sewer Project is currently in the planning phase.

  • Applied for Issue II funding October 2007

  • Ohio Public Works has approved funding

  • Public meeting to be held fall 2008

            

Contact:

Rhonda Boyd, P.E., P.S.

Senior Engineer

Phone: 330-678-8106

Email: boyd@kent-ohio.org

  City of Kent

Department of Public Service

Division of Engineering