Project Location:
Admore Drive (Stonewater Drive)
Project Budget: $650,000
Project Schedule:
Design Start Date November 2007
Construction Start Date July 2008
Project Finish November 2008
Admore Drive (Stonewater Drive)
The Admore Drive Extension project will connect West Main Street with the
Lakes at Franklin Mills Development and provide a new southerly access to Al
Lease Park from West Main Street with the construction of a 10’ wide asphalt
multi-use path.
The project involves the construction of new curbs, pavement, sidewalks,
storm sewer and waterline to update Admore Drive (Stonewater Drive) to the
current standards for an improved street. Existing utilities will also be
relocated underground.
This project also incorporates the installation of a traffic signal at the
intersection of Admore Drive (Stonewater Drive) and West Main Street to
accommodate the increase in traffic using this street for access.
The total project length is 735 feet (beginning at the West Main Street
intersection and heading north).
Project Status:
- Preliminary plans
being review
- Traffic signal design
fee being negotiated
- Coordinating with
utility companies
|