Admore Drive Extension
Project Location:
Admore Drive (Stonewater Drive)
Project Budget:
$1,060,000 ($353,000 from OPWC)
Project Schedule:
Design Start Date
November 2007
Construction Start Date July 2009
Project Finish
June 2010
Admore Drive (Stonewater Drive)

The Admore Drive Extension project will connect West Main Street with the
Lakes at Franklin Mills Development and provide a 1000’ long all purpose trail
from West Main Street. The construction of a 10’ wide asphalt multi-use path
will end at the existing bridge over Fish Creek. The trail will end south of Al
Lease Park due to an insufficient bridge width to safely carry both vehicles and
bikes.
The project involves the construction of new curbs, pavement, sidewalks,
storm sewer and waterline to update Admore Drive (Stonewater Drive) to the
current standards for an improved street. Existing utilities will also be
relocated underground.
This project also incorporates the installation of a traffic signal at the
intersection of Admore Drive (Stonewater Drive) and West Main Street to
accommodate the increase in traffic using this street for access.
The total project length is 1,400 feet (beginning at the West Main Street
intersection and heading north).
|